\n\t1.在坝体填筑中,层与层之间分段接头应错开一定距离,同时分段条带应与坝轴线平行布置,各分段之间不应形成过大的高差。接坡坡比一般缓于1:3。 \n2.坝体填筑中,为了保护黏土心墙或黏土斜墙不致长时间暴露在大气中遭受影响,一般都采用土、砂平起的施工方法。土、砂平起填筑,采用两种施工方法:一种是先土后砂法,即先填土料后填砂砾反滤料;另一种是先砂后土法,即先填砂砾反滤料后填土料。 \n3.对于坝身与混凝土结构物(如涵管、刺墙等)的连接,靠近混凝土结构物部位不能采用大型机械压实时,可采用小型机械夯或人工夯实。填土碾压时,要注意混凝土结构物两侧均衡填料压实,以免对其产生过大的侧向压力,影响其安全。\n<\/p>"},{"id":4522,"title":"土料的渗透系数大小主要取决于土的( )等。","stem":"","options":"颗粒形状^*@*^颗粒大小^*@*^水头^*@*^不均匀系数^*@*^水温","answer":"A,B,D,E","explanation":""},{"id":6324,"title":"根据《水利建筑工程预算定额》,一般土方开挖定额适用于( )。","stem":"","options":"一般明挖土方工程^*@*^上口宽超过16m的渠道^*@*^上口宽超过10m的渠道^*@*^上口面积大于80平方米柱坑土方工程^*@*^上口面积大于60平方米柱坑土方工程","answer":"A,B,D","explanation":""},{"id":5028,"title":"混凝土采用高效外加减水剂可( )。","stem":"","options":"节约水泥用量^*@*^减少混凝土的发热量^*@*^提高混凝土强度^*@*^提高混凝土极限拉伸值^*@*^提高混凝土早期强度","answer":"A,B,D,E","explanation":""},{"id":6328,"title":"根据《水利工程设计概(估)算编制规定》,人工预算单价包括( )。","stem":"","options":"基本工资^*@*^辅助工资^*@*^工资附加费^*@*^个人所得税^*@*^保险费","answer":"A,B,C","explanation":""},{"id":5436,"title":"应当公开招标的水利工程施工项目,经批准后可以进行邀请招标的情形包括( )等。","stem":"","options":"项目技术复杂或有特殊要求,只有少量几家潜在投标人可供选择的^*@*^受自然地域环境限制的^*@*^涉及国家安全、国家秘密,适宜招标但不宜公开招标的^*@*^拟公开招标的费用与项目的价值相比,不值得的^*@*^潜在投标人数量太多","answer":"A,B,C,D","explanation":""},{"id":6030,"title":"下列关于勘察设计单位的安全生产责任说法正确的有( )。","stem":"","options":"勘察(测)单位和有关勘察(测)人员应当对其勘察(测)成果负责^*@*^勘察(测)单位领导和有关勘察(测)人员应当对其勘察(测)成果负责^*@*^设计单位和有关设计人员应当对其设计成果负责^*@*^设计单位领导和有关设计人员应当对其设计成果负责^*@*^设计单位应当参与与设计有关的生产安全事故分析,并承担相应的责任","answer":"A,C,E","explanation":"
\n\t1.勘察(测)单位应当按照法律、法规和工程建设强制性标准进行勘察(测),提供的勘察(测)文件必须真实、准确,满足水利工程建设安全生产的需要。 \n勘察(测)单位在勘察(测)作业时,应当严格执行操作规程,采取措施保证各类管线、设施和周边建筑物、构筑物的安全。\n<\/p>\n
\n\t勘察(测)单位和有关勘察(测)人员应当对其勘察(测)成果负责。 \n2.设计单位应当按照法律、法规和工程建设强制性标准进行设计,并考虑项目周边环境对施工安全的影响,防止因设计不合理导致生产安全事故的发生。 \n设计单位应当考虑施工安全操作和防护的需要,对涉及施工安全的重点部位和环节在设计文件中注明,并对防范生产安全事故提出指导意见。 \n采用新结构、新材料、新工艺以及特殊结构的水利工程,设计单位应当在设计中提出保障施工作业人员安全和预防生产安全事故的措施建议。 \n设计单位和有关设计人员应当对其设计成果负责。 \n设计单位应当参与与设计有关的生产安全事故分析,并承担相应的责任。\n<\/p>"},{"id":6548,"title":"紧急防汛期间按规定调用的物资、设备、交通运输工具等,在汛期结束后应当及时归还,造成损坏或者无法归还的,按照国务院有关规定给予( )。","stem":"","options":"适当赔偿^*@*^适当补偿^*@*^修复^*@*^原价赔偿^*@*^其他处理","answer":"B,E","explanation":""},{"id":5812,"title":"以下是项目法人质量管理的主要内容有( )。","stem":"","options":"建立质量管理机构和质量管理制度^*@*^组织设计和施工单位进行设计交底^*@*^招标选择施工承包商并实行合同管理^*@*^委托质量监督机构对工程质量进行监督^*@*^完工后组织有关单位进行工程质量验收、签证","answer":"A,B,C","explanation":""},{"id":5277,"title":"水利工程建设项目的立项依据包括( )。","stem":"","options":"国家有关政策^*@*^项目建议书^*@*^已批准的江河流域综合治理规划^*@*^已批准的流域专业规划^*@*^可行性研究报告","answer":"A,C,D","explanation":""},{"id":6071,"title":"工程建设过程中,监理单位应认真履行以下职责( )。","stem":"","options":"参加设计单位组织的设计交底^*@*^签发设计单位的施工设计文件^*@*^负责进行施工单位资格审查^*@*^审批施工单位的施工组织设计、施工技术措施^*@*^按规定负责进行施工质量监督与控制","answer":"B,D,E","explanation":""},{"id":6392,"title":"水利工程建设项目施工监理的主要工作制度有( )。","stem":"","options":"技术文件审批制度^*@*^平行检测制度^*@*^工程验收制度^*@*^巡视检测制度^*@*^会议制度","answer":"A,C,E","explanation":""},{"id":6650,"title":"根据《混凝土面板堆石坝施工规范》(SL49-94),下列关于混凝土面板堆石坝施工的说法正确的是( )。","stem":"","options":"当确定未浇筑混凝土面板的坝体挡水时,必须对上游坡面进行碾压砂浆、喷射混凝土或喷洒阳离子乳化沥青等防渗固坡处理^*@*^坝体填筑开始前,应进行坝料碾压试验,优化相应的填筑压实参数^*@*^与趾板、岸坡接触的垫层应采用大型振动碾薄层碾压^*@*^垫层料、过渡料铺筑,应避免颗粒分离,分离严重部位应予掺混或挖除处理^*@*^趾板混凝土浇筑,应在相邻区堆石填筑后再进行","answer":"A,B,D","explanation":""},{"id":4519,"title":"防止土体发生流土渗透变形的工程措施主要有( )。","stem":"","options":"铺设反滤层^*@*^设置垂直防渗体^*@*^增加出口处盖重^*@*^设置排水沟或减压井^*@*^设置水平防渗体","answer":"B,C,D,E","explanation":""},{"id":4540,"title":"影响混凝土强度的因素主要有( )。","stem":"","options":"施工方法^*@*^水泥强度^*@*^浇筑强度^*@*^养护条件^*@*^水灰比","answer":"A,B,D,E","explanation":""},{"id":6021,"title":"应急公众信息交流应当做到( )。","stem":"","options":"水利部应急预案及相关信息公布范围至流域机构、省级水行政主管部门^*@*^项目法人制定的应急预案应当公布至工程各参建单位及相关责任人^*@*^项目法人制定的应急预案应向工程所在地人民政府及有关部门备案^*@*^应急预案应报当地人民政府审批^*@*^应急预案应通知当地政府各部门","answer":"A,B,C","explanation":""},{"id":4572,"title":"下列能改善混凝土耐久性的外加剂有( )。","stem":"","options":"泵送剂^*@*^引气剂^*@*^防水剂^*@*^速凝剂^*@*^缓凝剂","answer":"B,C","explanation":""},{"id":4620,"title":"围堰基坑初期排水流量大小主要考虑的因素有( )等。","stem":"","options":"地质情况^*@*^基坑大小^*@*^工程等级^*@*^工期长短^*@*^施工条件","answer":"A,C,D,E","explanation":""},{"id":6034,"title":"水利系统文明建设工地施工安全措施考核包括的内容( )。","stem":"","options":"施工安全事故处置方案^*@*^建立了以责任制为核心的安全管理和保证体系,配备了专职或兼职安全员^*@*^认真贯彻国家有关施工安全的各项规定和标准,并制定了安全保证制度^*@*^施工现场无不符合安全操作规程状况^*@*^一般伤亡事故控制在标准内,未发生重大安全事故","answer":"B,C,D,E","explanation":""},{"id":6156,"title":"分部工程质量评定合格标准为( )。","stem":"","options":"单元工程质量全部合格^*@*^金属结构及启闭机制造质量合格^*@*^中间产品质量及原材料质量全部合格^*@*^外观质量得分率达到70%以上^*@*^机电产品质量合格","answer":"A,B,C,E","explanation":""},{"id":4952,"title":"混凝土坝斜缝分块的原则包括( )。","stem":"","options":"缝是向上游或下游倾斜的^*@*^缝是向下游倾斜的^*@*^斜缝可以不进行接缝灌浆^*@*^斜缝不能直通到坝的上游面,以避免库水渗入缝内^*@*^斜缝必须进行接缝灌浆,否则库水渗入缝内","answer":"A,C,D","explanation":""},{"id":5303,"title":"关于中标通知书的说法,正确的有( )。","stem":"","options":"中标人确定后,招标人应当向中标人发出中标通知书^*@*^同时通知未中标人^*@*^必须在15个工作日之内签订合同^*@*^中标通知书对招标人具有法律约束力^*@*^中标通知书发出后,中标人可以放弃中标","answer":"A,B,D","explanation":""},{"id":4594,"title":"全段围堰法导流按其导流泄水建筑物的类型可分为( )。","stem":"","options":"明渠导流^*@*^束窄河床导流^*@*^隧洞导流^*@*^涵管导流^*@*^通过建筑物导流","answer":"A,C,D","explanation":""},{"id":5026,"title":"关于碾压混凝土坝施工质量控制的说法中,正确的有( )。","stem":"","options":"碾压混凝土坝一般采用VC值为10~30s的干贫混凝土^*@*^卸料、平仓、碾压主要是保证层间结合良好^*@*^碾压混凝土生产过程中,要严格控制配合比^*@*^在碾压过程中,要对碾压层的均匀性进行控制^*@*^施工过程中,通过检测碾压混凝土的湿密度和压实度控制强度","answer":"A,B,C,D","explanation":""},{"id":5118,"title":"水闸闸室止水缝部位混凝土浇筑,正确的做法是( )。","stem":"","options":"嵌固止水片的模板应适当提前拆模时间^*@*^浇筑混凝土时,不得冲撞止水片^*@*^水平止水片应在浇筑层的中间^*@*^振捣混凝土时,振捣器不得触及止水片^*@*^嵌固止水片的模板应适当推迟拆模时间","answer":"B,C,D,E","explanation":""},{"id":6697,"title":"根据《水利水电工程预应力锚索施工规范》(DL\/T5083-2004),重要岩体锚固或预应力混凝土结构工程,应进行下列( )。","stem":"","options":"材料试验^*@*^蠕变试验^*@*^破坏试验^*@*^锚索受力性能试验^*@*^验收试验","answer":"A,D,E","explanation":""},{"id":6499,"title":"在紧急防汛期,防汛指挥机构根据防汛抗洪的需要,有权决定采取的紧急措施有( )。","stem":"","options":"取土占地^*@*^爆破堤防^*@*^砍伐林木^*@*^清除阻水障碍物^*@*^拆除拦河闸","answer":"A,C,D","explanation":""},{"id":4526,"title":"根据《水利水电工程等级划分及洪水标准》(SL252-2000),下列永久建筑物可提高一级的有( )。","stem":"","options":"2级土石坝,坝高95m^*@*^3级土石坝,坝高75m^*@*^2级混凝土坝,坝高120m^*@*^3级混凝土坝,坝高110m^*@*^3级浆砌石坝,坝高110m","answer":"A,B,D,E","explanation":""},{"id":5299,"title":"水利工程建设施工项目符合下列具体范围并达到规模标准之一的水利工程建设项目必须进行招标。其中提到的具体范围是指( )。","stem":"","options":"关系社会公共利益、公共安全的水利工程建设项目^*@*^使用国有资金投资或者国家融资的水利工程建设项目^*@*^使用国际组织或外国政府贷款、援助资金的水利工程建设项目^*@*^社会团体融资的水利工程建设项目^*@*^集体自筹资金的水利工程建设项目","answer":"A,B,C","explanation":"
\n\t符合下列具体范围并达到规模标准之一的水利工程施工必须招标。 \t具体范围: \n(1)关系社会公共利益、公共安全的防洪、排涝、灌溉、水力发电、引(供)水、滩涂治理、水土保持、水资源保护等水利工程建设项目; \n(2)使用国有投资或者国家融资的水利工程建设项目; \n(3)使用国际组织或者外国政府贷款、援助资金的水利工程建设项目。\n<\/p>"}]
【正确答案】 正确答案